About the Project
In an ongoing effort to provide quality wireless service, Verizon has identified your community as one that will benefit from improved network coverage.
Milestone Towers is proposing a wireless telecommunications facility at Chopticon High School.
The proposal is for a 150-foot monopole and will include ground equipment required to operate the facility.
This equipment will be located at the base of the structure in a secure fenced area. Verizon will be the first wireless carrier to locate on the proposed tower.
Community Updates: News.
Lorem ipsum dolor sit amet, consectetur adipiscing elit, sed do eiusmod tempor incididunt ut labore et dolore magna aliqua. Ut enim ad minim veniam, quis nostrud exercitation ullamco laboris nisi ut aliquip ex ea commodo consequat. Duis aute irure dolor in reprehenderit in voluptate velit esse cillum dolore eu fugiat nulla pariatur. Excepteur sint occaecat cupidatat non proident, sunt in culpa qui officia deserunt mollit anim id est laborum.
Our Process
1. Due Diligence
Survey, FAA, FCC, NEPA, Phase 1, Geotechnical Analysis.
2. Land Use
Special Use Permit Application, Community Meeting, Staff Review, Planning Commission, Board of Supervisors.
3. Permitting
Conduct Bid Walk With Contractors and school representatives, submit permit application, 60 Day Review Period
4. Construction
Tower construction = 4-6 weeks | Carrier construction = 4-6 weeks on average
On-site supervision by Construction Manager | Schedule with schools to minimize disturbance to student activities.
5. Site Maintenance
Four visits per year for site maintenance | Remove trash, debris, check signage.
Annual RF testing | 2-4 visits per year for carrier modifications.